Victoria RIDS: what authorisation and approval evidence is still missing?
In short: For a Victorian restrictive-practice follow-up, keep the Authorised Program Officer's authorisation separate from any additional Victorian Senior Practitioner approval required. Identify the plan version and the evidence of each decision. NDPRO helps the practice review linked behaviour support plan (BSP) and restrictive-practice records, recorded status and expiry information; confirm what that information establishes against the responsible provider's official evidence.
A plan can have an Authorised Program Officer (APO) authorisation on file while another required decision still needs checking. For a team taking over the follow-up, “approved” alone does not explain who decided, what was covered or which evidence remains outstanding.
This guide helps a behaviour support practice organise that handover. It is published by NDPRO; the record below is a suggested administrative method, and the worked example is fictional.
Which Victorian decisions should be kept separate?
Victoria's authorisation process gives the APO responsibility for reviewing and authorising proposed restrictive practices for people supported by their organisation. Additional approval from the Victorian Senior Practitioner may also be required for specified practices and circumstances. Use the current detailed guidelines to establish what applies to the individual matter.
The Restrictive Intervention Data System (RIDS) supports the Victorian process. DFFH says APOs submit the behaviour support plan (BSP) through RIDS for authorisation. A file in your practice's storage is not, by itself, evidence of the required authorisation and any additional approval.
Start the check with three questions:
- Which proposed restrictive practice and BSP version does the APO decision cover?
- Does the applicable Victorian process also require Senior Practitioner approval?
- Where is the evidence of each required decision, including its period and conditions?
What should the receiving colleague be able to find?
Keep the question and the document that answers it together. The fields below propose a review record; they do not describe an automatic legal-pathway selector in NDPRO.
On a small screen, swipe across the table to read every column.
| Question | Evidence to locate | Who follows up | Keep separate from |
|---|---|---|---|
| Which plan is being considered? | BSP version and the relevant restrictive-practice description | Practitioner and implementing-provider contact | A previous plan with a similar name |
| What did the APO authorise? | Decision record, scope, period and conditions | Implementing provider's APO | The clinical review of the BSP |
| Is additional approval required? | The applicable guideline and the provider's confirmation of the required step | APO or appropriate Victorian authority | An assumption based only on a status label |
| Where is that approval? | Required Senior Practitioner decision or the outstanding request | Responsible implementing-provider contact | An application or acknowledgement of receipt |
| What remains open? | Missing document, accountable person and next review date | Practice coordinator | A task marked complete because an email was sent |
Use the period written in the actual decision. A plan review, an internal reminder and an authorisation expiry are different dates.
Fictional administrative example: the APO record is present
Alex coordinates a fictional specialist practice. The implementing provider supplies an APO authorisation reference linked to BSP version 3. The provider has identified that additional Senior Practitioner approval is required, but Alex cannot locate that decision in the handover.
- Evidence present: the APO record and its linked plan version.
- Question still open: where is the required additional approval, and does it cover this proposed practice?
- Follow-up owner: the implementing provider's nominated contact checks the official record with its APO.
- Evidence needed to close the question: the relevant decision, its reference and applicable conditions, reviewed against the plan being handed over.
The note remains “additional decision evidence to locate”. It does not turn into a completed approval because the APO document was received.
How does NDPRO support this check?
NDPRO brings restrictive-practice records and linked BSP references, recorded authorisation status and expiry information into the practice's review. Open those records to identify the matter, then check the supporting decision with the responsible provider.
For this Victorian handover, the useful outcome is a colleague understanding what the recorded status establishes and which question still needs an answer. The evidence table is a suggested method for that review, rather than a promise that every column is a separate software field.
The NDIS Commission's implementing-provider obligations remain separate: obtain the required authorisation, lodge its evidence and report use. The general authorisation guide explains that wider recordkeeping distinction.
Frequently asked questions
Does an APO authorisation always complete the Victorian process?
Check the applicable circumstances. The detailed Victorian guidelines distinguish APO authorisation from additional Senior Practitioner approval where required. Record both required outcomes rather than assuming one document answers every question.
Is a clinical supervisor's sign-off the same as state authorisation?
They serve different purposes. Keep the clinical review and the official restrictive-practice decisions identifiable, with their own evidence and responsible roles.
What should I ask to see in a software demonstration?